Document
11.09.2023 – Construcție ȘCOALĂ NOUĂ în sat.MIRCEȘTI, în cadrul Proiectului ȘCOLI MAI SIGURE, INCLUZIVE ȘI SUSTENABILE (SSIS). – Lb Engleza
Fișierul original pe site-ul primăriei
PDF · 2,1 MB · modificat pe site: 11.09.2023
Pagina sursă
Cum citez acest document
Document din 11.09.2023, „11.09.2023 – Construcție ȘCOALĂ NOUĂ în sat.MIRCEȘTI, în cadrul Proiectului ȘCOLI MAI SIGURE, INCLUZIVE ȘI SUSTENABILE (SSIS). – Lb Engleza”, Comuna Mircești, jud. Iași. Sursa: https://mircesti.ro/wp-content/uploads/2023/09/ESMP-Mircesti.pdf (arhivat pe acte-primarii.ro: https://acte-primarii.ro/iasi/mircesti/74443-11-09-2023-constructie-scoala-noua-in-sat-mircesti-in-cadrul-proiectului-scoli, 07.11.2026)
Semnalează o problemă (text greșit, date personale, document scos de primărie)
Pagina 1
MINISTRY OF EDUCATION
“Safer, Inclusive and Sustainable Schools” Project
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
„Vasile Alecsandri” Secondary School Mircești
Demolition and reconstruction
JULY 2023
1
Pagina 2
TABLE OF CONTENTS
ABREVIATIONS 3
1. GENERAL PROJECT AND ESMP INFORMATION 8
1.1 Project overview 8
1.2 Scope and objectives the ESMP 9
2. DESCRIPTION OF MIRCEȘTI „VASILE ALECSANDRI” SECONDARY SCHOOL
SUBPROJECT 11
2.1 Description of area and community affected by the investment 11
2.2 Mircești „Vasile Alecsandri” Secondary School 11
2.3. Location and characteristics of the site for investment 12
2.4 Proposed design for new school building 14
2.5 Associated Facilities 17
2.6 Temporary School Relocation Solution 17
2.7 Description of demolition and construction works expected 18
2.8 Temporary facilities required during the demolition and construction phase 19
3. ENVIRONMENTAL AND SOCIAL IMPACTS AND MITIGATION MEASURES 20
3.1 Key social risks and impacts 20
3.2 Social Impact Screening Process 20
3.3 Key environmental risks and impacts 23
3.4 Environmental and Social Management Plan 26
4. INSTITUTIONAL ARRANGEMENTS 33
5. THE PLAN FOR MONITORING SOCIAL AND ENVIRONMENTAL ASPECTS 37
6. STAKEHOLDER ENGAGEMENT AND INFORMATION DISCLOSURE 42
7. INVOLVEMENT OF INTERESTED PARTIES 46
8. GRIEVANCES MECHANISM 48
ANNEX 1 - REQUIREMENTS AND MEASURES WHEN HANDLING ASBESTOS 50
ANNEX 2 - PROCEDURE FOR MANAGEMENT OF PHYSICAL CULTURAL RESOURCES –
PROTECTION AND CHANCE FIND PROCEDURES 51
ANNEX 3 - FORM FOR SUBMITTING SUGGESTIONS / COMMENTS 52
2
Pagina 3
ABREVIATIONS
ACM Asbestos Containing Materials
CCEAR County Center for Educational Assistance and Resources
CSI County School Inspectorate
E&S Environmental and Social
EA Environmental Assessment
EC European Commission
EGO Emergency Governmental Ordinance
EIA Environmental Impact Assessment
EP Environmental Permit
EMP Environmental Management Plan
ESF Environmental and Social Framework
ESIA Environmental Social Impact Assessment
ESMF Environmental Social Management Framework
ESMP Environmental Social Management Plan
ESS Environmental and Social Standards
EU European Union
GBV Gender Based Violence
GD Governmental Decision
GO Governmental Ordinance
GRS Grievance Redress Service
LMP Labor Management Plan
MoE Ministry of Education
MEWF Ministry for the Environment, Water and Forests
MoC Ministry of Culture
OJR Official Journal of Romania
OP Operational Policy
SISSP Safer, Inclusive and Sustainable Schools Project
PMU Project Management Unit
3
Pagina 4
PMUMSUN Project Management Unit for the Modernization of the School
and University Network
POM Project Operation Manual
SEP Stakeholder Engagement Plan
TOR Terms of reference
WMP Waste Management Plans
WB World Bank
4
Pagina 5
EXECUTIVE SUMMARY
Introduction. The Secondary School „Vasile Alecsandri” Mircești has been selected under the „Safer,
Sustainable and Inclusive Schools Project” (SSISP) and will benefit from investments intended to
increase the quality and safety of the educational infrastructure. The Project aims to provide safer and
improved learning environments for students and teachers in selected schools, and to increase
institutional capacity for investing in sustainable education infrastructure.
The Project has been approved in 2021 and is implemented, over a period of six years, by the Ministry of
Education with financial support from the World Bank. It will address challenges related to issues of
safety, inclusion and sustainability in the school infrastructure in Romania. The five components under
the Project are: i) Demonstrating Integrated Investments in School Infrastructure, ii) Investing in Clever
Classrooms; iii) Foundations for Future Investments in Sustainable and Modern Schools Infrastructure;
iv) Project Management; and v) Contingent Emergency Response Component. More information about
the project can be found at https://umpmrsu.ro/sissp/descriere/.
Mircesti Subproject description. The building of the Secondary School „Vasile Alecsandri” in Mircești
dates from 1910 and it’s in an advanced state of degradation. The technical survey revealed a SR I Seismic
Risk, meaning that there is a major risk of collapse in the event of an earthquake. Due to the technical
state of the building and the poor conditions it offers, since 2018 the children were moved to the main
building of the school which was built in 1975 and is also in a poor technical condition; the technical
survey included this building in the seismic risk class SR II.
The proposed new building will have an area of 907 sqm and will host the 89 children currently enrolled
in primary and secondary education. The school will be aligned with the latest seismic standards, near
zero energy building standard, universal access for all children, adapted bathrooms for the needs of
teenage girls and people with disabilities, a cafeteria for lunch breaks and school events, among other
functions. The investment for the new school, including equipment and furniture, will be covered entirely
by Project funding, while some associated investments will be covered by the local authority, such as
demolition of the old school and annexes on the area planned for the new construction, playground area,
landscaping, courtyard lighting, alleys, utility connections, parking lots. These associated facilities will be
performed in parallel with the school construction and will be clearly defined under a Protocol between
the Project Management Unit for the Modernization of the School and University Network (PMUMSUN,
abbreviated in text as PMU) and Mircești local authority.
Environmental and Social Framework. The Project is financed by the World Bank and it is guided by
the Environmental and Social Framework of the institution (document available on the project website
at https://umpmrsu.ro/sissp/documente-cadru/), which supports green, resilient and inclusive
development by strengthening protections for people and the environment and making important
advances in areas such as labor, inclusion and non-discrimination, gender equity, climate change,
biodiversity, community health and safety, and stakeholder engagement. In addition to the design of the
new schools which will incorporate these elements, the Project aims at ensuring the protection of the
environment and the community during and after the school is being rebuilt. For this purpose, a series of
documents, frameworks and plans have been developed at the level of the Project in order to ensure the
safety of children, community members, workers, identify and mitigate adverse impacts during works,
and engage the local community in the process (Environmental and Social Management Framework,
Stakeholder Engagement Plan, Labor Management Plan, etc.). All these documents can be consulted on
the Project’s website https://umpmrsu.ro/sissp/.
Environmental and Social Management Plan (ESMP)
The ESMP outlines the main environmental and social risks associated with the investment in Mircesti.
The overall findings of the ESMP indicate short-term negative impacts on air, soil, water, and acoustic
environment during civil works. The environmental issues likely to be associated with the project
5
Pagina 6
activities include: noise generation, impact on soil and on water by the construction run-offs,
construction dust and wastes, and workers’ safety. However, these adverse impacts will be temporary
and site specific and will be mitigated through implementing adequate avoidance and/or mitigation
measures such as appropriate fencing, appropriate management of construction waste, H&S monitoring,
development of clear procedures on site, site-specific organization of the works.
The project is expected to have a mainly positive social impact at the level of the community by providing
a healthy and safe environment for future students and school staff members reducing the risks of
collapse and human accidents in case of an earthquake, contributing to the climate change adaptation
process, providing gender equity and universal access in the newly built facilities. In relation to potential
social risks, the ESMP addresses the children and community health and safety risks, including the risk
of accidents, disturbances to the educational activity and for neighboring residents, gender-based
violence risks, awareness in relation to disaster risks, exclusion of vulnerable groups from the benefits of
the investment, etc.
For this purpose, the ESMP proposes a set of mitigation measures and relies on community outreach and
consultations with those directly impacted (school staff, children, parents) and the community at large
to manage these risks across the different phases of the Project. A dedicated grievance mechanism will
assist the community to reach the Project in relation to any issues observed during Project
implementation.
A monitoring plan attached to the ESMP will be the basis for constantly checking compliance with the
proposed risk mitigation measures.
Institutional Responsibilities
The overall responsibility for implementing the provisions of the current ESMP lies with the PMU
dedicated for this project. The Mircesti local authority will also need to ensure compliance with the
provisions of the ESMP in relation to the works carried with local funding. All other actors involved in the
process, such as contractors, the Mircesti „Vasile Alecsandri” Secondary School representatives, will be
informed about their responsibilities and bidding documents, contracts and protocols will define roles,
timelines and actions expected from each stakeholder. The ESMF developed by the Project includes
guidelines and instructions for contractors to integrate in their own environmental and social
management plans, requested under their contracts.
Consultations and stakeholder engagement
Community and individual consultations began early in the project planning phase, aimed at collecting
initial views on the school design and allow for changes as needed. These consultations are guided by the
Stakeholder Engagement Plan developed for the Project, accessible on the Project’s website.
With the design contract signed in February 2023, a first round of consultations was held in Mircești with
representatives of local authorities, schools, teachers and representatives of students and parents, during
which general information about the project, the site plan and the proposed design for the new
construction in terms of spaces and functions, and the facilities proposed to make the building safer,
sustainable and inclusive were presented. Questions and suggestions from the participants were
recorded and a new consultation on the final design will be held in August 2023.
In relation to the current ESMP, this document will be disclosed and consulted with the community
during July and August 2023. The public consultations, as well as individual consultations where needed,
enable stakeholders to provide input that will help the implementation team to anticipate the impacts of
the project more accurately and design more appropriate and effective measures to manage the risks
generated. The consultation will be announced in advance at the level of the community and the
grievance mechanism will ensure communication channels before and after the consultations. A
community event disclosing the proposed design, as well as the provisions under the current ESMP will
6
Pagina 7
be organized by the school and local authority, with support from the Project during the disclosure of the
current ESMP in August 2023.
All Project materials, information and documents can be found at www.umpmrsu.ro.
Grievance Redress Mechanism. The GRM provides the community members and a range of other
stakeholders with the possibility to communicate their views, complaints, suggestions in relation to the
Project. This will give the possibility to mitigate any adverse environmental and social risks that the
project may encounter in its implementation as well as to give the community a permanent
communication channel with the Project.
The main four channels for receiving grievances are by website form on www.umpmrsu.ro , phone – (+4)
021 310 22 07, email – [email protected] and mail at the level of the PMU, Str. Spiru Haret, nr. 12,
Sector 1, București. This ensures that the PMU has an immediate control over all project related
grievances and can address the raised issues immediately.
The Project developed a Gender-based Violence Action Plan (part of the Stakeholder Engagement Plan)
in order to protect the community and staff from any cases of sexual harassment and exploitation. A
separate safe and confidential reporting channel for the incidence of gender-based violence is available
by e-mail address at [email protected] , or in person, by contacting the Project and requesting a
meeting with the social specialist on the team.
7
Pagina 8
1. GENERAL PROJECT AND ESMP INFORMATION
1.1 Project overview
Context of the Project
The proposed “Romania Safer, Inclusive and Sustainable Schools” Project addresses development
challenges related to issues of safety, inclusion and sustainability in the school infrastructure in Romania.
The Project has been approved in 2021 and is implemented, over a period of six years, by the Ministry of
Education with financial support from the World Bank 1 .
There is an urgent need to invest in quality and safe school infrastructure in Romania, with a high
proportion of school buildings failing to meet basic sanitary and safety standards and which pose a
substantial risk to lives in a future earthquake, a future pandemic and as the climate warms.
The Safer, Inclusive and Sustainable Schools Project (SISSP) aims to provide safer and improved learning
environments for students and teachers in selected schools, and to increase institutional capacity for
investing in sustainable education infrastructure. The investments in the participating schools will serve
as a demonstration of the preparation and implementation process of works to modernize and improve
school infrastructure. The Project is expected to lay the foundations for future investments through State
and European Union (EU) funds in school infrastructure. “Vasile Alecsandri” Secondary School in Mircești
has been selected to be part of the first batch of investments, together with other 22 schools in the
country. The technical design phase for “Vasile Alecsandri” Secondary School has commenced in
February 2023 and the construction works are estimated to begin starting early 2024. The main criteria
for school selection were the results of seismic risk assessments, together with school marginality data.
A list of all selection criteria and methodology can be found on the Project’s website.
Objectives
The SISSP Project aims to develop safer and better educational environments for students and teachers
in selected schools and to strengthen institutional capacity to invest in sustainable school infrastructure.
Components
The five components under the Project are: i) Demonstrating Integrated Investments in School
Infrastructure, ii) Investing in Clever Classrooms; iii) Foundations for Future Investments in Sustainable
and Modern Schools Infrastructure; iv) Project Management; and v) Contingent Emergency Response
Component.
The project will include:
a) Execution of construction works at selected educational units, in order to create a modern
infrastructure, resistant to earthquakes and other natural disasters and to increase operational safety;
b) The endowment with modern and flexible furniture, the endowment with digital equipment of the
classrooms in order to improve the quality of the educational process, the endowment with educational
materials that will allow the stimulation of the learning capacity;
c) Teacher training to improve digital skills and understanding modern alternative methods that will
encourage active student participation, group work / social learning and will be sensitive to students'
individual motivations and differences;
d) Providing institutional support to local authorities for accessing European funds that will be available
in the financial year 2021-2027 in order to make investments in modernization of school infrastructure;
1 The Board of the WB approved on 29th of April 2021 a Loan on the amount of 100 million euros (EUR)
(equivalent to USD 121,07 million) to Romania for the implementation of the SISS Project. The Loan Agreement
Number 9236-RO was signed between the WB and the GoR, represented by MoF, on 6th of May 2021 and it is in the
process of ratification. The SISS Project is to be implemented over a period of six years, between 2021 and 2027.
8
Pagina 9
e) Training of students, teachers and community awareness by promoting actions that can be taken to
build disaster resilience and climate change, disaster preparedness and response, opportunities to
increase sustainability (such as zero waste, water harvesting, energy use and conservation, etc.).
1.2 Scope and objectives the ESMP
The Project is supported by the World Bank through an Investment Project Financing Instrument. As a
consequence, the Borrower is required to identify and assess the environmental and social risks
associated with the Project and to propose an integrated management of these risks throughout the
preparation and implementation phases. This process is carried under the World Bank Environmental
and Social Framework (ESF) that enables the WB and Borrowers to better manage environmental and
social risks of projects and to improve development outcomes.
The Bank believes that the application of these standards, by focusing on the identification and
management of environmental and social risks, will support Borrowers in their goal to reduce poverty
and increase prosperity in a sustainable manner for the benefit of the environment and their citizens. The
standards will: (a) support Borrowers in achieving good international practice relating to environmental
and social sustainability; (b) assist Borrowers in fulfilling their national and international environmental
and social obligations; (c) enhance nondiscrimination, transparency, participation, accountability and
governance; and (d) enhance the sustainable development outcomes of projects through ongoing
stakeholder engagement.
The objective of the current ESMP, developed in the specific context of the "Vasile Alecsandri" Secondary
School Mircești sub-project is to ensure that the social and environmental impacts that may occur in the
implementation of the “Vasile Alecsandri” Secondary School Mircești sub-project activities are
adequately addressed through appropriate mitigation measures, integrated in the processes of
implementation and operation of the sub-project, in order to ensure the protection of the environment
and human health. This objective is in line with the Environmental and Social Management Framework,
a document that was prepared by the Project in 2020, at project design level, and which incorporates all
the requirements that are applicable to the project, as well as main risks and mitigation measures to be
implemented across all investments.
The development of the current ESMP is based on the provisions of World Bank’s Environmental and
Social Framework (ESF) that requires Borrowers to assess and manage environmental and social risks of
projects supported by the WB. The ESF is built upon the 10 WB’s Environmental and Social Standards
(ESS), out which, the following six apply to the SISSP and establish the standards that the Borrower and
the project will meet through the project life cycle, as follows:
ESS1: Assessment and Management of ESS Risks and Impacts;
ESS2: Labor and Working Conditions;
ESS3: Resource Efficiency and Pollution Prevention;
ESS4: Community Health and Safety;
ESS8: Cultural Heritage This ESS8; even though not applicable to subproject the standard is
relevant to “Chance finds procedure in the ESMF” as the civil work activities are likely to have risks and
impacts on cultural heritage;
ESS10: Information Disclosure and Stakeholder Engagement.
The ESSs that apply to the project have been analyzed and adapted to the context in Romania and a series
of tools and documents have been elaborated in the Project Preparation phase in 2020. These
instruments include the Environmental and Social Management Framework, Stakeholder Engagement
Plan, Labor Management Plan, Grievance Redress Procedure, Gender Based Violence Action Plan, etc. In
addition, two studies carried by the World Bank in the context of the Project, assessing the specific needs
and concerns of different vulnerable categories that might be impacted by the investments in schools,
have informed the Project design. All these documents can be consulted on the Project’s website.
9
Pagina 10
The Environmental and Social Management Framework also contains a review of applicable Romanian
legislation, in addition to an in-depth presentation of the World Bank’s standards.
10
Pagina 11
2. DESCRIPTION OF MIRCEȘTI „VASILE ALECSANDRI” SECONDARY SCHOOL SUBPROJECT
2.1 Description of area and community affected by the investment
Mircești is a small rural administrative territorial unit located on the west side of Iasi County, near the
border with Neamț County. The administrative unit consists of Mircești and Iugani villages at a distance
of about 4 km.
The population is divided between the two villages with a significantly higher number of people settled
in Iugani, where almost all the inhabitants have adopted the Roman Catholic confession.
According to the census conducted in 2011, the number of citizens at the level of the Mircești
administrative unit was 3750 persons. More recent data based on residency, provided by the local
authorities indicate that at the end of 2021, the number of residents in the administrative unit was 3895
but the preliminary results of 2021 census reported a population of 3338. The difference can be explained
by large parts of the population that still have IDs with their address in the settlement, but have
temporary or permanently migrated to other regions or countries.
According to data available on the National Institute of Statistics website, in the last 10 years the
population of the village has decreased by about 3.7% and the number of children aged 6 to 14 years has
decreased by 17.5% in the same period 2.
The number of children school-aged has constantly decreased in the past decade, and there is no sign of
increasing school populations. However, the current overcrowding situation and the technical condition
of the buildings of the school suggest that the educational capacity is not sufficient to serve the needs of
the community.
2.2 Mircești „Vasile Alecsandri” Secondary School
"Vasile Alecsandri" Secondary School’s building in Mircești was selected in the first batch of 23 schools
that will be the object of investments within the project. The school building was considered eligible
because it is located in an area with seismic risk, it has a high risk of collapse in case of earthquake
(according to the technical expertise, the building falls into the category of seismic risk class SR I, it is in
an advanced state of degradation, is located on the public domain and has not undergone recent complete
renovation / consolidation works. The building is 113 years old.
The existing school infrastructure in the locality consists of the Secondary School "Vasile Alecsandri"
(legal entity), which also includes the Iugani Secondary School and two kindergartens, one in each village.
In 2018, for safety reasons, the school decided to move the children from the old building to the main
school building in the same courtyard. This building was built in 1975 and has 8 classrooms. The building
has not been maintained lately, the roof is damaged and there is water infiltration and the windows are
not tight, which leads to high heating costs in the cold season. The recent technical expertise has classified
the building in seismic risk class SR II.
There are 89 children enrolled in the school in Mircești, 45 of them in three primary classes - I, II and IV
and 44 children in three secondary classes - VI, VII and VIII. A kindergarten group also operates in the
same building. Educational activities are organized in such a way that there are currently no groups of
children of different years learning simultaneously in one classroom. For this purpose, children from
Mircești enrolled in preparatory class, the third class and the fifth class are transported to the school in
Iugani to complete the number of children needed to form a class.
There are 181 children enrolled at the Iugani school and classes are formed for all years of study. As the
school building has 7 classrooms, the school's teacher-room has been set up to accommodate teaching
2 According to the National Institute of Statistics online database http://statistici.insse.ro:8077/tempoonline/#/pages/tables/insse-table accesed on 10 April 2023
11
Pagina 12
activities. Additional space has also been rented in a nearby building where children in the preparatory
class are learning.
Of the 8 classrooms available at the school in Mircești only 6 are occupied. Although one of the classrooms
in Mircești school is not used and could receive a class from Iugani school, this option was not preferred
because most of the children are from Iugani and the conditions in Mircești school are worse due to the
technical state of the building.
The new building that will be erected under the Project is designed to host the current 6 classes of the
school and the old building is planned to be rehabilitated and rearranged to host two kindergarten groups
and the sports classes during bad weather periods.
2.3. Location and characteristics of the site for investment
The results of the technical documentation revealed the need to demolish the existing building and
construct the new one in a different location on the school site.
The site of the investment consists of a land plot of 8449 sqm that is registered as a public land of the
local authority, located on the Școlii Street no. 177. The description below details some of the main
characteristics of the proposed site for construction:
Description of the current school building proposed for demolition and reconstruction:
Year of Construction It was built in 1910 with the destination of school;
Area and functions The building has an area of 351 sqm, 4 classrooms, and housed the
teaching activity for the primary classes of the school;
Seismic risk category The technical expertise indicated the highest seismic risk, class I;
Current access to utilities: The building does not have toilets;
The building is connected to the electrical network;
The heating is provided by wood stoves installed in each room;
Current universal access Currently the building does not provide facilities for universal access;
situation
Conclusion of the technical The conclusion of the technical expertise indicates the risk of partial or
expertise total collapse in case of an earthquake, and argues the financial efforts
to consolidate the existing building are not justified, with the proposal
to demolish and construct a new building.
The proposed land hosts the headquarters of the Secondary School "Vasile Alecsandri" Mircești, with the
building in which educational activities are currently carried out, the old building that will be demolished,
a sports field and 4 annexes used as deposits.
12
Pagina 13
Fig. 1 The buildings on the school`s site and the vicinities
Vicinities: the land is bordered by Școlii Street, County Road 208R, the Police Station, and private
properties; the area is mainly residential and the City Hall and a library are located near the site.
The current access to the school and in the proposed design is made from Școlii Street.
The land does not include historical buildings and is not located in the protection area of any historical
monument.
Fig. 2. The building proposed for demolition, C2 in yellow
13
Pagina 14
The figure above indicates the constructions on site:
C1 – Main building of the school, built in 1975 and currently used for educational activities;
C2 – the old school building, subject to the investment which will be demolished;
C3, C4, C5, C7 – deposits;
C8 - recently built sports terrain.
2.4 Proposed design for new school building
Key features of design as provided by the architect team
The new school project aims to integrate and bring to life the latest best practice in contemporary school
design:
▪ Integration of technology
▪ Safety and security
▪ Transparency
▪ Multi-purpose space
▪ Outdoor learning
The basic principle of the project is the safe and efficient operation of the spaces, based on sustainability
principles. The designed systems aim at producing energy from renewable sources, limiting
consumption, environmental control and ease of maintenance, reducing operating and maintenance
costs, protecting the environment and increasing operational safety, with the main objective of
implementing the NZEB concept as efficiently as possible.
Fig. 3 Designer renderings of the interior of the new building
14
Pagina 15
The proposed new building will have a built area of 907 sqm and a developed area of 1750 sqm. The new
school will be able to host the 89 children currently enrolled in primary and secondary education and
will have a maximum capacity of 156 students. The school will be aligned with the latest seismic
standards, near zero energy building technology, universal access for all children, adapted bathrooms for
the needs of teenage girls, a cafeteria for lunch breaks and school events.
Fig. 4 Proposed emplacement of the new school
The spatial-functional organization of the proposed building includes the following spaces:
▪ 6 classrooms;
▪ 2 laboratories (one for computer science and one for chemistry, both equipped with storage
space);
▪ 1 dedicated area for documentation, research, and information activities;
▪ 1 library;
▪ 1 cafeteria designed to simultaneously serve meals in two shifts, equipped with a
handwashing/disinfection area, a counter area for serving meals, a storage area and an office
space;
▪ 1 administrative area for teachers, consisting of a school office, a secretary's office, a principal's
office, and a staff room;
▪ 1 medical office for consultations and treatments, including an isolation room;
15
Pagina 16
▪ 1 psychological counseling office with a special room for calming children with special
educational needs;
▪ storage spaces for cleaning materials and technical areas dedicated to equipment ensuring the
lighting, heating, cooling, and ventilation of the building, as well as those with fire protection
purposes.
The building will provide sanitary facilities (sinks, upward jet faucets, and toilets) for students
and teachers in accordance with the current legislation, as well as storage spaces for cleaning
materials.
The proposed building is designed to accommodate individuals with disabilities, with access
points, horizontal and vertical connections, space dimensions and furniture designed in
accordance with the provisions of applicable regulations. All level differences, ramps, and stairs
are properly marked, and vertical accessibility for individuals with mobility impairments is
ensured through the use of an elevator. Both levels of the building are equipped with specially
sized and equipped restroom facilities to meet the needs of these individuals.
Fig. 5 Proposed plan for the new construction (ground floor)
16
Pagina 17
Fig. 6 Proposed plans for the new construction (first floor)
2.5 Associated Facilities
Given the limited resources at the level of the Project and the priority to increase the seismic safety of
children in schools at risk across the country, some of the associated elements of the investments will be
funded and implemented by local authorities, considering budgetary availability at local level. From an
environmental and social perspective, these associated investments will be approached as Associated
Facilities of the Investment.
Associated Facilities means facilities or activities that are not funded as part of the Project and, in the
judgment of the World Bank, are: (a) directly and significantly related to the project; and (b) carried out,
or planned to be carried out, contemporaneously with the project; and (c) necessary for the project to be
viable and would not have been constructed, expanded or conducted if the project did not exist.
The E&S standards of the Project, defined under the current ESMP, will apply to these Associated
Facilities. In practice, the requirements under the current ESMP will apply to all Contractors, irrespective
of the contracted works (demolitions, constructions, landscaping, etc.). The PMU will assist the local
authority in implementing and monitoring the measures set out in the current ESMP for the associated
facilities.
Description of interventions expected to be carried by the local authorities:
▪ Demolition of the building that hosted the school until 2018;
▪ Playground area next to the school;
▪ Alleys, courtyard lighting and benches, and landscaping;
▪ Parking lots;
▪ Utility connections for the proposed new building.
2.6 Temporary School Relocation Solution
Students have already been relocated since 2018 to the C1 building of the school, which has sufficient
classrooms to accommodate the relocated children. The C1 building was built in 1975 and according to
the expert's report in 2022 it was classified as seismic risk class RS II. The building has not been
maintained recently, the roof is damaged, there is water infiltration and the carpentry is worn out.
17
Pagina 18
The subproject will need a mobile classroom solution to accommodate the educational and
extracurricular activities during the demolition and construction works.
The mobile classroom will comprise of several containers arranged in a fluid manner to accommodate
the functions of the educational activities. It will provide similar functions as a standard building, with
separate toilets for girls and boys, classrooms, heating units, lighting, standard furniture. The site will
need to be prepared in advance by the local authority and will include the connection to electricity, water
and wastewater. Heating will be ensured by electrical heaters.
The solution will be consulted with the school representatives, local authority and school community
(parents, teachers, children). The costs associated with the mobile classrooms will be under the
responsibility of the Project, while the preparation of the site and utility connection will fall under the
responsibility of the local authority in Mircești.
Fig. 7 Examples of modular classrooms in Bucharest and Constanța
2.7 Description of demolition and construction works expected
The demolition will be contracted by the local authority. The works are expected to take two months and
will be carried under strict guidance outlined in the technical design documentation associated with the
demolition process, prepared under the responsibility of the local authority in Mircești. The process will
involve the disconnection of the current buildings from utilities, the set-up of the construction site within
the premises (offices, toilets, changing rooms for staff) and temporary connection to utilities, the fencing
and restrictions of accessing the site, equipping the site with health and safety equipment, providing
training to workers on site, set-up of environmental protection measures (vehicles washing, transport of
debris, protection of green spaces on the construction site).
The technological process of demolition will involve the use of vehicles and machinery specific to
construction works such as bulldozers, excavators, jackhammers and dump trucks. The trucks that will
go in and out of the site will undergo a wheel washing process and will be covered to avoid the overspill
of debris on public roads. A project information board and a grievance system board and letter box will
assure that both community members and site workers will be able to communicate any grievances and
suggestions to the project team, in relation to the demolition process.
The construction of the new building will most probably last between 12 and 18 months. The first period
will be allocated to the to the site preparation for the construction of the new building and the installation
of the necessary equipment for the construction works (site organization).
18
Pagina 19
The new building will have a built area of 907,00 sqm and a developed area of 1750,00 sqm. The
infrastructure of the building is made of insulated foundations under the superstructure columns and
reinforced concrete beams. A general excavation will be carried out on the whole surface of the building
for the foundations. A layer of sand and gravel is placed under the slab above ground level to break the
capillarity. Thermal insulation of the above ground slab will be made with 20 cm thick extruded
polystyrene. Horizontal waterproofing will be provided under the ground floor walls to prevent damp.
The superstructure of the building consists of reinforced concrete frames composed of columns, beams
and reinforced concrete slabs. Access to the first floor will be via two reinforced concrete staircases.
The roof will be of non-circulating terrace type, with heat-sealing membrane. On the main access area, a
porch will be built by removing the cantilever slab over the floor, with reinforced concrete structure,
continuing the non-circulating terrace roofing.
The external enclosures will be made of 30 cm thick BCA masonry, thermally insulated with a ventilated
facade system with a 15 cm thick basalt plaster thermosystem. The interior partitions will be made of 30
cm thick BCA masonry for the teaching areas and 15 cm thick for the other areas. The exterior joinery
will be aluminium, glazed, low-e, 4s, with a minimum corrected resistance of 0.83 m2K/W and the curtain
wall in the main entrance area will be double-glazed, low-e, 4s, with a minimum corrected resistance of
0.77 m2K/W. The interior joinery will be aluminium, with full panel and glass panel. The interior floors
will be made with PVC carpet. In wet areas (sanitary), non-slip ceramic tiles will be used. Walls and
ceilings will be plastered, sanded and painted with super washable paint. The ceilings will be made of
plasterboard with 60x120 cm sound-absorbing panels.
2.8 Temporary facilities required during the demolition and construction phase
Demolition and construction activities will require temporary installations on site. The installation of
these facilities will allow the performance of various functions of the site, including the storage of building
materials, waste management, the arrangement of offices, dedicated spaces for workers and the
provision of health and safety on the site.
All the temporary facilities will be installed inside the site subject to works. The construction site will be
installed on the ground and will include the placement of modular containers to serve as offices, changing
rooms for site workers and as a warehouse for equipment. Ecological toilets will be installed on the site,
and their contents will be constantly emptied by the supplier. Separated toilets for women will be
installed, if necessary. A truck washing platform will be provided to clean the wheels of trucks leaving the
site during demolition and construction work.
At the entrance to the site, a panel dedicated to the mechanism for receiving petitions/complaints with a
related grievance box will be installed. Construction workers will be informed about the possibility of
contacting the PMU or of submitting an anonymous complaint about the working conditions and the
health and safety provisions on the spot, in addition to the grievance mechanism that is expected to
function at the level of the Contractors.
The temporary facilities required during the construction works will take into account the designation of
spaces for the storage of materials, washing and decontamination facilities for vehicles, contamination
control points, ecological toilets, wastewater treatment services, offices and night lighting. Special
attention will be given to the security of the site. Appropriate fencing and controlled access to the site will
be ensured and the works related traffic will be organized in a manner that will not put at risk the
activities and persons in the vicinity (educational activities, children playing in the school playground,
neighbors, passers-by). The noise and dust levels will be constantly monitored and appropriate measures
will be taken to keep them under the legally admitted maximum, as indicated in the sections below. All
these measures will be captured in the Project detailed design documentation, the bidding documents
and the contracts signed with designated construction companies.
19
Pagina 20
3. ENVIRONMENTAL AND SOCIAL IMPACTS AND MITIGATION MEASURES
3.1 Key social risks and impacts
The project is expected to have a considerable positive impact at the level of the Mircești community,
children and teachers. This project aims that teachers and students have access to schools that are safe
from earthquake, fire and other disaster and climate risks, meet minimum standards for sanitation,
heating, ventilation, are energy efficient, can safely resume during health pandemics, such as Covid-19,
and provide universal access to students with disabilities.
By providing a comprehensive solution, through a single investment, the community can reduce dropout
or early school leaving, increase educational outcomes and provide safe learning environments.
Strengthening disaster resilience and emergency infrastructure in severely damaged buildings at the
level of selected units across Romania, will increase the chances of communities to be safely assisted in
the event of disasters and will also provide improved and standardized working conditions for the
employees and users of these facilities.
In relation to the WB’s ESF, the social development and inclusion under the Project aims at empowering
all people to participate in, and benefit from, the development process. Inclusion encompasses policies
to promote equality and nondiscrimination by improving the access of all people, including the poor and
disadvantaged, to the educational services that will result from the investment. It also embraces action
to remove barriers against those who are often excluded from the development process, such as women,
children, persons with disabilities, youth and minorities, and to ensure that the voice of all can be heard.
3.2 Social Impact Screening Process
Regarding the vulnerable categories that might be impacted by the Project, two research studies carried
by the World Bank in 2020 in the context of the Project preparation, namely, a Community Vulnerability
Assessment and a Roma Children Learning Experiences Assessment revealed several aspects that
contribute to the objectives of the planned investments. The two studies carried interviews with children
and parents coming from vulnerable and marginalized communities, and concluded several interventions
that can be addressed by the project in order to improve the experience of vulnerable children in the
newly built schools (e.g. adding cafeterias for hot meal programs, adapting to the needs of children with
disabilities, addressing the lack of access to modern technologies for children from poor environments,
etc.).
An environmental and social checklist was developed at project design stage, including elements related
to the social and environmental context of the investments. Several site visits and consultations with
relevant stakeholders have also informed the social risk assessment related to the Mircești sub-project.
The specific aspects that informed the risk analysis are:
▪ No land acquisition is involved in the process, as all work will be carried on the same public land
that hosts the present building and that is in the property of the local authority in Mircești;
▪ The land plot that hosts the current building serves other buildings and functions, such as the
other school building, a sports field, and annexes that served other purposes in the past (e.g., slag
deposit, warehouses, etc.);
▪ The site is bordered by a county and a local road, the Police Station and residential units.
However, none of these are considered sensitive in relation to the demolition and construction
process;
▪ The current building is not a cultural heritage building and is not located in the protection area of
a historical monument;
▪ For safety reasons the students are relocated since 2018 in the C1 building of the school, built in
1975. The relocation building lacks recent maintenance works and is included in the seismic risk
SR II category; the Project will provide a mobile classroom solution to host the school activities
during the construction period.
20
Pagina 21
▪ At the other local secondary school - located in Iugani settlement - 181 children are enrolled in 9
classes and the building has 7 classrooms; in order to accommodate all 9 classes, the chancellery
has been converted into a classroom and additional space has been rented for the preparatory
class and the kindergarten, in a nearby building.
Social risks identified under Project Activities:
The social risks identified at this stage are based on data collected at the level of Mircești, through
checklists, observational site visits, consultations, and similar civil works projects. The categorization of
the social risk listed below addresses the demolition and reconstruction works that will be involved in
the project, organized under three stages (1) pre-construction, (2) demolition and construction works,
(3) post-construction.
Project preparation
▪ Reduced access of vulnerable categories in consultations and project information related to
the Mircești investment. By vulnerable groups, the Project understands: children and families
living in poverty, elderly, children and persons with disabilities, women, Roma children and
adults, children with special educational needs. The project not only aims at avoiding or
mitigating adverse impacts on these categories, that could potentially be more impacted by the
Project, but seeks to create development opportunities for the marginalized. In the case of the
community of Mircești, vulnerable groups are considered to be children and families living in
poverty, children with disabilities and special educational needs, Roma children and their
families, children in the other school building which is currently overcrowded.
▪ Lack of specific measures to accommodate the needs of students/teachers with disabilities
and children with special educational needs in the sub-project design. The inclusion
component of the Project enhances universal access design so that people with health conditions
or impairments can enjoy all the benefits provided by the new school, including adapted
furniture, dedicated spaces for counseling and inclusive technology solutions. The proposals that
came from the community during the first round of consultations will be expected to be included
in the design specifications.
▪ Reduced access to education for relocated children, in case the mobile classrooms are non-
compliant with health and safety requirements and the functional needs of the educational
process (e.g., fire safety, sanitation, lack of heating, lack of sound proofing, lack of light, etc.). Any
faults that are not taken into account during design and construction risk to reduce children’s
access to education.
Construction of the new school:
▪ General discomfort generated by dust and noise pollution for children who will remain in the
current school building or will be relocated to mobile classrooms, the children playing around the
school next to the construction site, for teachers, nearby residents.
▪ Community health and safety risks generated by the construction site, in the form of possible
accidents, especially in relation to children learning and playing next to the site, in situations
involving lack of fencing and security measures to restrict access on the construction site, Risk of
road accidents for pedestrians in general, and for children, generated by temporary heavy
transport during the construction process.
▪ Disruptions in utility services due to accidents or planned interventions (water, sewerage,
electricity, gas).
21
Pagina 22
▪ Occupational accidents on the construction site, especially in relation to migrant workers, if
the case; the construction sector in Romania continues to be the sector with the highest rates of
work related accidents and fatalities, due to the lack of compliance with health and safety rules
on site. In relation to the increased number of foreign workers, these persons are likely to be more
exposed to occupational accidents due to language barriers.
▪ Social tensions, increased risks of sexual harassment, abuse and violence, misconduct
during works, potentially perpetuated by construction workers. This impact will likely be greater
in the event of installing temporary accommodation for construction staff, given the proximity of
the site to current educational activities; the risk is related to a gender-based violence risks. The
screening process that concluded the need to protect the local community, especially children
and women, from such situations that might be generated by the presence of contracted workers
in Mircești.
Post-construction phase
▪ Lack of opportunities for vulnerable groups to benefit from the investment, such as Roma, in
particular Roma children, children currently learning in buildings at risk, community at large. The
risk considers the demographic decrease of school aged children in Mircești. The school will also
have the potential to become a community asset that can be used by various groups outside of
the educational activities, irrespective of their status within the community. Other risks related
to vulnerable categories are the lack of specific equipment to accommodate the needs of children
with disabilities and special educational needs, or the misuse of the menstrual hygiene units for
teenage girls.
▪ Reduced disaster awareness in relation to the role the new school can play in the event of a
natural disaster, as well as the process of protecting the life of children and other community
members in the event of an earthquake or other natural disaster. Beyond the infrastructural
component, the project aims at addressing the lack of disaster preventive actions at the level of
the school and the community at large.
▪ Limited availability of the newly built school and facilities due to lack of local funds to cover
associated facilities that do not fall under the investment as well as day to day operational and
maintenance expenses of the new school; the proposed designs are aiming to create energy
efficient buildings that are likely to reduce the current operational expenses of local budgets.
Associated investments that will be carried by the local authority (fencing, alleys, public lighting,
landscaping, playgrounds) will be captured in the proposed design and will be planned in advance
so that the new school building is ready to use at the end of Project investments.
Social risks identified under Associated Facilities:
Given the focus of the project on enhancing the safety of children learning in schools with considerable
seismic risk, some of the associated investments, such as demolition of current buildings (including the
old school and clearing the current site from the three annexes), and fencing, alleys, parking lots, public
lighting, playground area, landscaping at the site of the new school, will be carried technically and
financially by the local authorities.
The risks that pertain from this activity are similar in nature as those described above, under the new
construction works, and will be addressed by local authorities:
▪ Community health and safety risks for the all children and staff of the school, for the users of
the sports facility in the schoolyard as well as neighbors and passers-by during the demolition
and construction activities. Securing the perimeter of the building and managing the heavy traffic
are considered essential in keeping the safety of children and adults intact during the process.
22
Pagina 23
▪ Occupational health and safety. As mentioned above, occupational accidents in the
construction sector continue to be an area of high risk for human health, as enforcement of
national legislation tends to be low, especially in works located in rural parts of the country.
▪ General discomfort generated by dust and noise pollution for children learning and playing
in the nearby school building and in the schoolyard next to the site, teachers, nearby residents,
staff and beneficiaries of the institutions near the site.
▪ Risk of road accidents for pedestrians in general, and for children in particular, generated by
temporary heavy transport during the construction process.
▪ Disruptions in utility services due to accidents or planned interventions (water, sewerage,
electricity).
3.3 Key environmental risks and impacts
3.3.1 Screening and permitting processes
An initial E&S screening was performed by the City Hall and this was then revised by the Environmental
and Social Safeguards Specialists of the PMU. Site visits and consultations with the school and local
authorities representatives further supported the data collection process.
Further environmental impacts will be highlighted in the permitting process the Environmental Impact
Assessment procedure which will be conducted by the County Environmental Protection Agency based
on the documents provided by Technical Design Consultant and results will be incorporated into the
current Environmental and Social Management Plan, if necessary.
Environmental Screening results:
Mircești is located in Suceava Plateau, in Siret River basin. School location is inside a 8449 sqm
plot, being the Public ownership of Locality;
The land plot allocated for the investment is located outside the area with flooding probability
(Fig. 8, source https://rowater.ro/despre-noi/descrierea-activitatii/managementul-situatiilor-
de-urgenta/directiva-inundatii-2007-60-ce/harti-de-hazard-si-risc-la-inundatii/). No landslide
probability was identified;
Land clearing will be performed during demolition works. Construction works do not need
extensive land clearing being located in a separate area than the old school. On the site there is
reasonable space for typical construction areas;
The nearby road is rural and with normal traffic. Low hazards to public traffic and pedestrian by
transportation vehicles during construction activities are anticipated;
At 550 m distance is the Vasile Alecsandri Complex with the Memorial House, Park and
Mausoleum IS-II-m-B-04202. However, this does not impact the Project.
23
Pagina 24
Fig. 8 Flooding hazard map
Environmental risks identified under Project Activities
Demolition and construction work:
▪ Pollution with dust, noise and noxious emissions;
▪ Transportation and construction vehicles impact on pedestrian and general traffic;
▪ Improper management of waste resulted from demolition/construction works;
▪ Asbestos impact during demolition of building (low probability);
▪ Improper management of Sewage waters from working site and Leakages from
equipment used on working site;
▪ Not following the indicated procedure in case of discovering a physical cultural, historical
or archaeological resource during excavation or demolition.
Operation of the new school:
▪ Improper waste management by not allocating enough recipients for selective collection
and storage of waste (household, plastic, glass, metal, paper, electric and electronic waste)
- low probability;
▪ Unsafe practices during operation of the building by improper connections to the sewage
network - low probability.
The mitigation measures proposed by the Project with the aim of avoiding or reducing as much as
possible the impacts and risks listed above are included in the management plan below, that defines
impact areas, mitigation measures and institutional responsibilities associated with the proposed
measures.
24
Pagina 25
Environmental Guidance
Energy Efficiency, Insulation and Ventilation
Insulation should be tailored to the seasonal impacts of climate, internal thermal load, and characteristics
of exposure. Vapor barriers should prevent moisture intrusion in the roof insulation and outer wall
cavities and using damp course.
Window location should be determined on view, ventilation, light, thermal gain, privacy control and
interior space functions.
High-efficiency systems for heating domestic water (including solar systems) and for interior space
heating should be selected with maintenance and long-term running costs in mind.
Plumbing should be coordinated to minimize plumbing and also water service to toilets and utility rooms.
Water-saving faucets, ring mains and other devices also require consideration. Construction materials
will conform to national regulations and internationally accepted standards of safety and environmental
impacts.
Electrical Systems
Incoming cables should be located underground. Main entrance feed and panel located away from places
of work and waiting is prudent in avoidance of electromagnetic fields. Ground faulty wiring near any
plumbing fixture is a precaution. Selecting the most energy efficient light fixtures, lamps, appliances and
equipment will reduce energy demand but can introduce undesirable electromagnetic fields. Be aware
that close proximity to table, floor and desk halogen, fluorescent and other high-efficiency fixtures and
lamps can cause an exposure to harmful electromagnetic fields.
Selection of Construction Materials and Construction Methods
Environmentally sound goods and services should be selected. Priority should be given to products
meeting standards for recognized international or national symbols. Traditionally well-tried materials
and methods should be chosen before new and unknown techniques. Construction sites should be fenced
off in order to prevent entry of public, and general safety measures would be imposed. Temporary
inconveniences due to construction works should be minimized through planning and coordination with
contractors, neighbors and authorities. In densely populated areas, noisy or vibration generating
activities should be strictly confined to the daytime.
Handling of Waste
The handling of construction debris will be according to local and national regulations, and as specified
in the ESMP, and described above under site considerations. These regulations are developed and
enforceable in Romania. Monitoring will be the responsibility of site supervisors working for the MoE.
For asbestos and asbestos-containing materials please see Annex 1. In all the specific cases for which
contractors should demolish or remove asbestos-containing materials, these categories of works should
be done only with qualified personnel and fully in line with the specific legislation related to this specific
field.
Occupational Health and Safety At Work
The contractor has the obligation to ensure all necessary personal protective equipment (PPE) and
materials, and the workers have the obligation to use all such protective equipment - helmets, gloves,
goggles where appropriate and work uniforms. All these minimum protection rules, doubled by avoiding
over-exhaustion of workers, prevent ergonomic injuries and other work-related accidents resulting from
repetitive, excessive and manual handling of building materials.
25
Pagina 26
Recommendations for their prevention and control include knowledge of the most common causes of
wounds in construction and decommissioning by:
▪ Training of workers in the lifting and handling of materials, techniques in construction and
decommissioning projects, including placement of weight limits over which mechanical
assistance is required;
▪ Workplace site planning to minimize the need for manual heavy load transfer;
▪ Selecting tools and designing workstations that reduce the need for strength;
▪ Implement administrative controls in work processes, such as job rotation and rest breaks.
Contractor H&SP and ERP
Contractor will be required to produce a Health and Safety Plan (H&SP) and an Emergency Response Plan
(ERP) to protect his employees during the works he shall undertake. This Plan will be reviewed at the
level of the PMU both on Environmental and Social aspects and at the level of the Bank. The Contractor’s
ESMP (C-ESMP) shall be considered when preparing contractor’s H&SP and ERP. Environmental controls
and exposure levels associated with worker protection shall be included in the C-ESMP. Work practices
required by the ESMP are not intended to compromise health and safety in any way. Each H&SP and ERP
will be approved by the Supervising Engineer prior to the contractor commencing works to ensure
adequate health and safety controls and procedures have been developed, that are appropriate to the
works to be undertaken.
3.4 Environmental and Social Management Plan
The mitigation measures proposed by the Project with the aim of avoiding or reducing as much as
possible the impacts and risks listed above are included in the management plan below, that defines
impact areas, mitigation measures and institutional responsibilities associated with the proposed
measures. The plan will be subject to consultations with stakeholders and to updates during
implementation, whenever necessary.
26
Pagina 27
E&S Impact Area and Risks Proposed mitigation measures Institutional responsibility for
mitigation
Pre-construction phase
General E&S Management The Contractor shall develop a Contractors ESMP in accordance with the All Contractors
requirements stipulated throughout the ESMP. C-ESMP will include Labor
Risks: unsafe and unsustainable Management Plan, Occupational Health and Safety Plan, Solid Waste
practices during demolition and Management Plan, Emergency Response Plan;
construction works;
Contractor to provide reports and access to E&S information related to the
Affected persons: school children and implementation of this ESMP;
staff, community members, workers;
Project Design Ensure all elements derived from consultations are integrated into the final PMU E&S specialists
design, especially universal access features;
Risks: exclusion of community from
project design, risks of accidents for Provide clear elements for community safety in Site Organization Plan Design Consultant
children, community and workers, non- (fencing, restricted access, site surveillance/security system);
compliant plans at the level of site
organization;
Affected persons: vulnerable
categories, school children and staff,
community members, workers;
Safe Relocation of Children Ensure health and safety conditions in relocated space are compliant with PMU (applying checklist and
minimum norms; managing grievances)
Risks: unsafe conditions for relocated Apply health and safety checklist and propose remediation actions in the
children and staff, exclusion of event of non-compliance;
vulnerable categories from educational
activities; Install Grievance Box at the relocated school; Local authority (for remediating
actions and installing grievance box)
Affected persons: relocated children
and staff, vulnerable categories, such as
disabled children/staff;
Construction and Demolition Phase
27
Pagina 28
E&S Impact Area and Risks Proposed mitigation measures Institutional responsibility for
mitigation
Community Health and Safety Community Safety Elements in place prior to commencement of works and Contractor
maintained throughout work schedule (fencing, designation of areas with
Risks: lack of safety and protective restricted access, separate access routes with ID check-up, clear and visible
elements resulting in accidents, access signaling panels, surveillance/security system);
of children in restricted areas; Waste Management Plan, Traffic Management Plan, Worker Management
Plan, OHS Plan, Emergency Response Plan approved by the PMU;
Record and communicate any accidents involving community members to
Affected persons: children, school staff, the PMU;
community living next to construction Installation of GRM Board and Box next to Construction site.
sites;
Information Notes submitted to all neighbors in relation to work schedules PMU Community Engagement
and grievance mechanism; Specialist
Children Safety Awareness Actions developed at the level of the school with School and local authority
support from PMU.
Occupational Health and Safety OHS Plan and Emergency Response Plan approved by site manager and all All Contractors
safety elements in place in accordance with national legislation and site
Risk: occupational accidents, lack of management plan;
protective equipment on site, lack of Provide translation of OHS requirements on site for Contractors employing
contracts and illegal work, lack of foreign workers;
appropriate trainings; OHS Training plan included in Labor Management Plan;
Internal Code of conduct and Grievance Mechanism for Workers disclosed
to workers;
Affected persons: workers across all Ensure workers are using Personal Protection Equipment and World Bank
planned demolition and construction Health and Safety guidelines are followed;
works; Inform the PMU of any accidents occurring on site or non-compliance
signaled by the control of designated authorities;
Appropriate signaling and information boards on H&S installed at the sites;
PMU’s E&S Specialists and PMU’s
Perform ad-hoc site visits to check compliance with national H&S
technical area coordinator
requirements;
Pollution with dust, noise and Consult and agree with school and church representatives on avoiding, as All Contractors
noxious emissions much as possible, noise pollution during educational/religious services;
GRM Board and box installed at site;
28
Pagina 29
E&S Impact Area and Risks Proposed mitigation measures Institutional responsibility for
mitigation
Risks: unsafe conditions for educational Vehicles and machines will be properly maintained and will have up-to-
activities, non-compliant work date technical revisions;
schedules, disturbances at the level of Fencing with acoustic barriers in the school direction;
neighboring activities; Covering the transportation vehicles for demolition or excavation
materials;
Affected persons: school children and Cleaning wheels of vehicles at the exit from working site;
staff, neighbors;
Inform community/neighboring properties on any planned or accidental PMU’s Community Engagement
interruptions in utility services;
Specialist and Area coordinators
Information Notes submitted to all neighbors in relation to work schedules
and grievance mechanism;
Traffic Management Traffic Management Plan elaborated under the C-ESMP; All Contractors
Organize the transport related to the construction works as to avoid the
Risks: road accidents and restricted hours with high pedestrian traffic next to school (early
access for emergency services; morning/afternoon);
Separate pedestrian access to the school from construction vehicles
Affected persons: children, elderly, accessing the site;
community members, neighbors; Install signaling of routes, restricted access and speed limits on site;
Request support from Local Police to assist with children safety during
School and local authority
intense transport schedule, if necessary;
Children Safety Awareness Actions developed at the level of the school with
support from PMU.
Influx of Labor Contractor will comply with PMU’s Labor Management Plan, attached to the All Contractors
bidding documents;
Risks: sexual harassment and abuse of Trainings regarding SEA/SH will be provided to all Project workers, based
school children and other community on contractor’s Code of Conduct, signed by all workers;
members, especially girls and women, Inform PMU on intention to temporary house workers on site and present
and female workforce, social tensions in accommodation plans and features.
the community, illegal work practices; Provide separate facilities for women, if there is female participation in
works on site;
Affected persons: school children, girls Ensure that all site workers have legal contracting forms, are over 18, have
and women in the community and valid working visa for foreign workers;
working on site, workers, especially Provide internal grievance mechanism for workers and inform about
migrant workers; Project’s GRM;
29
Pagina 30
E&S Impact Area and Risks Proposed mitigation measures Institutional responsibility for
mitigation
Inform PMU on non-compliances recorded by auditing labor authorities;
The Gender Based Violence Action Plan, including service provider PMU’s Social and Community
mapping, updated as necessary in the Project’s SEP;
Engagement Specialists
Awareness actions on GBV Plan to be carried at the level of the
school/community, with the support of PMU;
Dedicated grievance channel to capture SEA/SH related complaints in
place;
Waste Management Management of waste from demolition/construction in order to be All contractors
reutilized, recycled and other, for minimum 70% of generated waste;
Risks: pollution; Separated collection of domestic waste in designated areas on working site;
Contracting authorized companies for waste transport and management;
Affected parts: air and soil
Sewage waters from working site Supply of working site with mobile toilets for workers and company All contractors
personnel;
Leakages from equipment used on Using equipment in good conditions to avoid Leakages;
working site Removing contaminated soil, treating and final deposing;
Risks: pollution;
Affected parts: soil and underground
waters;
Clearing the site and removal of Any removal of existing trees will be replanted in a suitable area; All contractors
planted vegetation Restoration of vegetation to the initial state, wherever applicable;
Impact on trees vegetation or
hedgerows
Risks: damages;
Affected parts: vegetation;
30
Pagina 31
E&S Impact Area and Risks Proposed mitigation measures Institutional responsibility for
mitigation
Discovering a physical cultural, Stop the construction activities in the area of the chance find; All contractors
historical or archaeological resource Delineate the discovered site or area and Secure the site;
during excavation or demolition Notify the Supervising Engineer who in turn will notify the responsible authorities
immediately (within 24 hours or less);
Risks: damages; Construction works could resume only after permission is granted from the
responsible local authorities concerning safeguard of the physical cultural resource;
Affected parts: cultural heritage;
Asbestos impact during demolition of In case of finding asbestos and asbestos-containing materials during demolition - Contracted companies for demolition
building contract with authorized companies for handling, collection, transportation and works
disposal;
Risks: pollution;
Affected persons: workers;
Post Construction Phase
Lack of opportunities for vulnerable Consult school and parents on inclusive school furniture during acquisition PMU’s Community Engagement
groups phase; Specialist
Consult girls on menstrual hygiene practices and provisions in the
Risks: lack of adapting the equipment to dedicated spaces in the new buildings;
the needs of vulnerable children, Consult with vulnerable groups if there are instances of exclusion or
especially children with disabilities and discrimination in relation to accessing the new school;
special educational needs, vulnerable Ensure acquisition documents reflect community perspectives derived
girls; from all consultations;
Affected persons: children with
disabilities and special educational
needs, girls coming from poor families;
Limited functionality of the new Detailed design and associated costs will be consulted with the Local PMU Management
building or delays due to lack of local authority and financing options will be identified in the Protocol signed
funds for associated facilities between the parties;
assumed under the PMU-Local Protocol will clearly state the timelines related to the associated facilities
Authority Protocol related to the functionality, accessibility and safety of the new building and
its surroundings;
Risks: lack of universal accessibility to
the new building, lack of safety for
31
Pagina 32
E&S Impact Area and Risks Proposed mitigation measures Institutional responsibility for
mitigation
children (especially girls) next to the
school area, lack of connection to basic
utilities;
Affected persons: school children and
staff, girls, children with disabilities;
Waste resulted from school activities Improper waste management due to insufficient allocation of recipients for School maintenance staff
selective collection and storage of waste (household, plastic, glass, metal,
Risks: pollution paper, electric and electronic waste);
Affected parts: air and soil
Leakages of sewage waters Maintenance in good condition of sewage network; School maintenance staff
Risks: pollution;
Affected parts: soil and underground
waters;
32
Pagina 33
4. INSTITUTIONAL ARRANGEMENTS
The overall responsibility for implementing the provisions of the current ESMP lies with the PMU
dedicated for this project. All other actors involved in the process, such as contractors, the Mircești
School representatives, local authority, will be informed about their responsibilities and bidding
documents, contracts and protocols will define roles, timelines and actions expected from each
stakeholder.
Definition of roles and responsibilities (PIU/local authorities/Contractors/)
PMU roles and responsibilities in relation with ESMP
The Project Management Unit for the Modernization of the School and University Network (PMUMSUN)
within the Ministry of Education acts as the Project Implementing Agency. The PMU is responsible for
all Project implementation activities. PMU will be assisted in the process by a TD & TA Consultant,
Contractors for Construction Works, specialized technical verifiers (including environmental verifiers),
site managers, contract managers, who will be contracted in different phases of the Project.
Role of the Technical Design & Technical Assistance Consultant
At the time of writing this report, PMUMSUN have procured the services of a Consultant who would
provide the Technical Design documentation for the demolition and construction works and Technical
Assistance during works execution. In more detail, the Consultant will be responsible with the
development of the Inception Report, with the delivery of the Documentation for obtaining the
Demolition Permit for the existing construction, with the Documentation for obtaining the Building
Permit, with the development of the Technical Design and of the Execution Detail Design for the
proposed construction, and with providing the Technical Assistance Services for the works execution,
as well as preparing the necessary documentations for obtaining the operational permits, and other
necessary services in order to achieve the investment objective of the Mircești School. In relation to the
ESMP, the Consultant will:
Supervision of the quality of the works, including compliance with Law No. 10/1995 - in terms
of requirements:
▪ A - Mechanical strength and stability
▪ B - Fire safety
▪ C - Hygiene, health and environment
▪ D - Safety and accessibility in operation
▪ E - Noise protection
▪ F - Energy saving and thermal insulation
The worksite organization (including details on waste management, sewerage during works,
separate toilets, dining and resting spaces, health and safety signage, grievance board, project
information board, fencing, restricted access);
Provide the specifications for the works, where ESMP provisions should be included.
The PMU E&S experts will be involved in regular meetings with the Consultant, and will participate in
site visits together, review the monthly reports submitted by the Consultant in relation to ESMP
provisions, and update the ESMP based on details and specifications that will have surfaced during the
technical design phase. An initial public consultation took place in March 2023 and a second
33
Pagina 34
consultation is planned while disclosing this document, presenting the proposed final design of the new
school, allowing the participation of the public in the design and planning process.
Role of the Environmental, Social and Community Engagement Specialists
Environmental, Social and Community Engagement Specialists within PMUMSUN will be responsible
for disclosure, consultation, coordination and supervision of the ESMP and risk mitigation measures
undertaken within the project. The Specialists will work in close coordination with supervision project
coordination staff and technical staff in courts and will:
disseminate existing environmental and social management guidelines and develop guidelines
in relation to issues not covered by the existing regulations, in line with the Bank and EU
standards for implementation, monitoring and evaluation of mitigation measures;
ensure that procurement processes for construction works and supply of equipment include
reference to appropriate guidelines and standards;
conduct periodic site visits to inspect and approve plans and monitor compliance;
ensure the uniformity in all activities related to the preparation and implementation
of Environmental and Social Management Plans;
keep permanent contact with Environmental and Social safeguards specialists of the World
Bank and ask for advice on any problem that requires guidance regarding the activity in the
field.
In particular the Environmental Specialist will:
perform activities related to compliance of environmental activities;
prepare activity plans for Environmental impact mitigation of the construction activity
outcomes and the Environmental monitoring plan;
ensure that the systematic supervision in relation with qualitative and quantitative indicators
and perform analysis for underlining the achievements and the evolution of the implementation
process is done by Contractors according to the monitoring plan;
prepare periodical reports for the World Bank and Government Agencies;
coordinate environmental training for staff, designers and local contractors, related to
responsibilities on environmental protection.
In particular the Social Specialist will:
ensure that the terms of reference for any design consultancy services incorporate the World
Bank safeguards and corporate requirements including public disclosure and public
consultation on the results of environmental and social impact assessments, citizen engagement
and gender aspects;
be responsible for carrying out activities related to social safeguards within the framework of
component 1 of the project in accordance with the provisions of the loan agreement;
manage the GRM, and ensures that each complaint is handled in accordance with the procedure;
reviews the complaints received and recommends appropriate measures to deal with the issues
raised, as appropriate;
monitor the social impact of the Project and propose measures to properly manage the risks
generated by the implementation activities.
In particular the Community Engagement Specialist will:
identify the stakeholders and organize stakeholder engagement activities that will be targeted
at project affected persons as well as at other interested parties;
34
Pagina 35
be responsible of the communications, consultations and engagement with direct beneficiaries
and the wider public;
ensure outreach to and engagement of disadvantaged and vulnerable groups;
establish and manage public meetings, trainings and workshops, media and social media
communication, disclosure of written materials, as well as a survey among affected persons to
gauge satisfaction with the quality of citizen engagement and share additional concerns.
Role of the Contractors
The contractor shall be responsible for implementing the provisions under the ESMP. The final version
of the ESMP, with updated actions based on the technical design and specifications provided by the
TD&TA Consultant, will be approved after the contribution of the public, collected during public
disclosure and consultations and organized during the technical design phase. Once the contract is
signed, with the ESMP acting as an annex, the Contractor can bring contributions to the plan, following
negotiations with the E&S experts within the PMU and the TD&TA Consultant.
Contractor ESMP (C-ESMP)
The demolition and construction contractors will prepare their own ESMP based on the framework of
the approved site-specific ESMP. The C-ESMP will be reviewed and approved by the Supervising
Engineer and will form part of the contractual obligations. The C-ESMP will be specific to the contracted
services but will consider the impact of these services at the level of the construction sites.
Worksite organization
Constructor will implement all the aspects from the works project design including details on waste
management, sewerage during works, separate toilets, dining and resting spaces, health and safety
signage, grievance board, project information board, fencing, restricted access.
Occupational Health and Safety at Work
The contractor has the obligation to ensure all necessary protective equipment and materials, and the
workers have the obligation to use all such protective equipment - helmets, gloves, goggles where
appropriate and work uniforms. All these minimum protection rules, doubled by avoiding overexhaustion of workers, prevent ergonomic injuries and other work-related accidents resulting from
repetitive, excessive and manual handling of building materials.
Recommendations for their prevention and control include knowledge of the most common causes of
wounds in construction and decommissioning by:
Training of workers in the lifting and handling of materials, techniques in construction and
decommissioning projects, including placement of weight limits over which mechanical
assistance is required;
Workplace site planning to minimize the need for manual heavy load transfer;
Selecting tools and designing workstations that reduce the need for strength;
Implement administrative controls in work processes, such as job rotation and rest breaks.
Contractor H&SP and ERP
Contractor will be required to produce a Health and Safety Plan (H&SP) and an Emergency Response
Plan (ERP) to protect his employees during the works he shall undertake. The C-ESMP shall be
considered when preparing contractor’s H&SP and ERP. Environmental controls and exposure levels
associated with worker protection shall be included in the contractor’s ESMP. Work practices required
by the ESMP are not intended to compromise health and safety in any way. Each H&SP and ERP will be
approved by the Supervising Engineer prior to the contractor commencing works to ensure adequate
35
Pagina 36
health and safety controls and procedures have been developed, that are appropriate to the works to
be undertaken.
The bidding documents will include requirements related to all plans, strategies and resources allocated
for the current ESMP compliance. The ESMF that informs the current ESMP contains detailed
information about legal obligations, World Bank requirements and specific guidelines for Contractors
to develop all necessary documents.
Role of the Site Manager
The site manager will facilitate the monitoring visits and will need to be organized in accordance with
the ESMP provisions. The bidding documents for the procurement of the site managers will include
revisions from the E&S experts within the PMU.
Role of the Local Authority
The local authority in Mircești will be responsible with contracting and monitoring the E&S
performance of demolition and construction works carried for the Associated Facilities. This
responsibility will be subject to the Protocol signed between the PMU and the local authority. Trainings
will be provided to ensure that compliance of this ESMP are reflected in bidding documents. Monitoring
of E&S aspects will be carried by the local authority, with support and supervision from the PMU.
Role of the Mircești School
The Mircești School will assist the PMU with the implementation of awareness campaigns aimed at
preparing children and staff in relation to safety next to the construction site, disaster risk campaigns,
gender based violence risks and the grievance mechanism at the level of the Project.
36
Pagina 37
5. THE PLAN FOR MONITORING SOCIAL AND ENVIRONMENTAL ASPECTS
Monitoring plan for risks/mitigation measures
The mitigation measures proposed under the social and environmental management plan (ESMP) will
be monitored by the responsible entities during the implementation of the sub-project, as described in
the Monitoring Plan below.
Monitoring activities aim at:
monitoring and reporting on the effectiveness of the mitigation measures and responsibilities
identified and achieved;
informing about the need to extend, intensify or adjust mitigation measures;
identifying any new areas potentially exposed to the environmental and social impact that have
not been taken into account in the ESMP.
Monitoring will begin with the construction work and will be implemented at all stages of the project.
A presentation of the social and environmental monitoring plan is presented below.
The monitoring plan will be updated, if needed, once all permitting is obtained or during
implementation, if unexpected impacts generate new mitigation measures in the management plan.
37
Pagina 38
Environmental and Social Monitoring Plan
E&S Measures/ Monitoring Actions Monitoring Institutional responsibility for
Parameters Frequency monitoring
Pre-Construction
General E&S Management C-ESMP has been developed and Approved; Once (prior to PMU’s E&S Specialists
construction works)
Project Design Detailed design incorporates community perspectives from Once (finalization of PMU’s E&S Specialists
consultations and specific safety features for community detailed design)
safety;
Relocated School’s Safety Health and safety Checklist completed and remediation Once (as soon as Local authority with technical
actions (if necessary) implemented practical) support from PMU
GRM Box installed at relocated school;
Construction/Demolition Works
Community Health and Community Safety Elements in place at Once (prior to PMU’s E&S Specialists
Safety construction/demolition sites; commencement of
works) and during
site visits
Recorded Grievances on site/other channels and recorded Weekly PMU
accidents and their resolution;
Report on community health and safety; Monthly Contractors
Children Safety Awareness Actions implemented; Once (prior to PMU Community Engagement
construction works) Specialist
and according to
agreed plans
38
Pagina 39
E&S Measures/ Monitoring Actions Monitoring Institutional responsibility for
Parameters Frequency monitoring
Information Notes on Work Schedule distributed to Once (prior to PMU Community engagement
affected stakeholders; construction works) Specialist
Occupational Health and Occupational H&S elements in place (PPE, first aid, training Once (prior to works PMU E&S Specialists and Area
Safety list, H&S responsible, signaling, code of conduct, etc.) commencement) and Coordinator
assessed during site visits; during site visits
Daily
Contractors’ H&S expert
Reports on occupational health and safety; Monthly Contractors’ H&S expert
General discomfort Construction and demolition works carried in accordance Daily Contractors
generated by dust and noise within agreed timelines and hours;
pollution at the level of
school/neighboring area
Recorded Grievances on site/other channels and recorded During Site Visits and PMU’s Social and Community
accidents and their resolution; when grievances are Engagement Specialist
recorded
Compliance with noise and dust mitigations measures; Daily Contractor
During site visits PMU’s Environmental Specialist
Traffic Management Separated access, signaling and driver’s safety training in Once (prior to Contractor
place; construction works)
Compliance of traffic measures; During site visits PMU
Influx of Labor Trainings on Code of Conduct (including GBV) and Once (prior to Contractor
Contractor’s Grievance Mechanism for Workers performed construction works)
for all workers on site;
39
Pagina 40
E&S Measures/ Monitoring Actions Monitoring Institutional responsibility for
Parameters Frequency monitoring
Resolution of grievances related to conduct of workers Whenever PMU’s Social and Community
(including GBV) in the school area/community; grievances are engagement specialists
recorded
Compliance with Labor Management Plan attached to During site visits PMU’s Social Specialist
contract;
Collection and transport of Review the transportation list and conditions at the storage Before the Environmental Specialist of
demolition or hazardous facility; transportation of the Contracted company for
waste (including asbestos) hazardous waste demolition and construction
works
Environmental Safeguards
Specialist of PMU
Dust, noise and noxious Visual checks and according with the procedure for During the Environmental Specialist of
emission demolition; demolition phase Contracted company for
and clean-up demolition works / Constructor
activities Area coordinator of the PMU
Environmental Safeguards
Specialist of PMU
Good functioning of Visual checks and according with the procedure for During the Environmental Specialist of
construction machinery demolition; demolition phase Contracted company for
and clean-up demolition works / Constructor
activities Area coordinator of the PMU
Environmental Safeguards
Specialist of PMU
The safety protection Visual checks; At the beginning of Contractors’ H&S expert
measures applied for the each working day
workers during the project
activities
During site visits Area coordinator of the PMU
40
Pagina 41
E&S Measures/ Monitoring Actions Monitoring Institutional responsibility for
Parameters Frequency monitoring
Discovering a physical Reported discoveries during demolition/excavation; During demolition Contractor
cultural resource, such as and excavations Environmental Safeguards
(but not limited to) Specialist of PMU
archeological sites, historical
sites, remains and objects, or
a cemetery and/or
individual graves during
excavation or construction
Asbestos impact during Records of quantity of asbestos materials discovered; Whenever such Contractor
demolition of building discoveries are made Environmental Safeguards
Specialist of PMU
Post-Construction
Lack of opportunities for Consultations with vulnerable groups implemented; Once (prior to PMU’s Community Engagement
vulnerable groups acquisition of Expert
equipment)
Reduced awareness in Completed trainings at the level of the school; Once (at the roll-out PMU
relation to the role that the of the trainings)
newly/rehabilitated school
can play in the event of a Report on community event and actions carried at the Once PMU
natural disaster opening of the school;
Waste resulted from school Verification of Separated collection of waste and e-waste in Monthly School administrative staff
activities designated area;
Leakage of Sewage waters Checking the sewage collection systems Monthly School administrative staff
41
Pagina 42
6. STAKEHOLDER ENGAGEMENT AND INFORMATION DISCLOSURE
The project is expected to have a minimal negative impact on neighboring properties. However, the
noise and dust from the construction, the process of relocation of students and other inconveniences
that can be experienced by the local community in Mircești as a result of demolition and construction
work are elements that show that the project affects the lives of others and all necessary measures must
be taken to keep in touch with those affected, to understand their fears, discomfort and to consider their
suggestions in order to mitigate as much as possible the adverse impact on them.
In earlier stages of the project, consultations were held with representatives of local authorities,
schools, teachers and representatives of students and parents, during which general information about
the project, the site plan and the proposed construction in terms of spaces and functions, and the
facilities proposed to make the building safer, sustainable and inclusive were presented.
The parties interested or affected by the works to be carried out under the Mircești sub-project
identified at this stage are listed below.
▪ Representatives of the Secondary School, including staff from the Iugani schools;
▪ Student`s and parent`s representatives: The students' council from the Mircești Secondary
School, the parents' committee representative (including representatives from Iugani);
▪ Employees and beneficiaries of the institution on the vicinity of the site – the Police Station
and the Library;
▪ People living in the vicinity of the site;
▪ Citizens potentially affected by utility shortages during works.
Other Interested Parties:
The population of Mircești;
Employees of the technical design consultants that will be carrying tasks on site;
Local NGOs on social development (representing persons with disabilities, elderly, Roma
inclusion, poverty relief, etc.) and environment protection;
Local authorities in Mircești: the city mayor, social assistance department, Local police
Media outlets in Mircești;
Environmental Agency, Environmental Guard;
Iași County School Inspectorate;
Iași County Center for Educational Assistance and Resources.
Vulnerable groups
The Community Vulnerability Assessment carried during Project preparation revealed that
disadvantaged/vulnerable individuals and groups relevant to the project fall into two broad categories:
on one hand, there are vulnerable subgroups among the selected schools’ students; on the other, there
are vulnerable subgroups within the local communities.
Within the school communities, it appears that the following groups would be particularly vulnerable:
children from poor rural areas, children from Roma groups, children from other ethnicities, pregnant
girls and young mothers, school dropouts, children with special educational needs, children with
physical disabilities, distressed children, bullied kids.
At the level of the community, persons or groups that would be particularly vulnerable include people
with visual or hearing impairments, Illiterate community members or members with low education
levels, working parents of schoolchildren, etc.
42
Pagina 43
Regarding the Mircești sub-project, the involvement of interested parties and the dissemination of
information will be adapted to the specific needs of the Roma community in the nearby settlement,
children with disabilities and special educational needs and their parents, parents who have difficulties
accessing written information, people elderly people who live in the vicinity of demolition and
construction sites.
Stakeholder engagement activities include establishment and management of a project-wide grievance
redress mechanism, public consultations, community events to disclose information and consult wider
audiences, trainings and workshops, media and social media communication, disclosure of written
materials in the village, individual discussions and focus groups with specific groups, as well as the
application of surveys among affected persons to gauge satisfaction with the quality of citizen
engagement and to provide the possibility of different groups to share additional concerns.
Engagement and communication activities
The communication and engagement activities include information disclosure, public consultations,
media communication and direct interactions with stakeholders as follows:
Updated information on www.umpmrsu.ro about the project implementation, ESMP disclosure,
timing of consultations, grievance mechanism, relocation of students, etc.;
Social media posts and engagement on the Project’s dedicated Facebook page;
Public consultations with relevant stakeholders and affected parties related to the design of the
new school, ESMP, relocation, equipping the school, and whenever necessary;
Information disclosure at the level of the community through posters, announcements on the
local authority and school webpages and social media accounts, information leaflets made
available at school level, use of existing channels for parents and teachers (such as WhatsApp
groups or Facebook groups);
Press releases related to the important stages of the project, including the requirements of the
ESMP and the results of the monitoring efforts related to the compliance with the environmental
and social requirements (for example, public consultations), as necessary;
Email updates sent to stakeholders on stages of the Project, invitations to public consultations,
results of monitoring activities;
Face to face meetings, especially with categories that are under-represented or vulnerable in
relation to the Project (e.g. Roma community members and representatives, elderly persons
affected by the Project, persons having difficulties in accessing written materials or information
made available online).
Consultations carried by the Project
During the project identification and preparation stage in 2020, several consultations took place at the
national level involving with the Council of Students, County School Inspectorates, National Federation
of Parents' Associations, schools, local councils, other agencies and key stakeholders. In addition, an
online survey completed by 480 persons informed the Project about perception of the state of their
school building, the availability of modern teaching resources of the school, the existence of a school
emergency plan, building safety, accessibility and quality, possible challenges linked to the building’s
demolition/reconstruction, preferred channels for information and feedback provision, etc.
Regarding the Mircești sub-project, in 2021 consultations were held with school representatives and
the local authority to identify the needs of the local educational infrastructure at risk.
43
Pagina 44
On 08.03.2023, the initial consultation took place within the SSIS-Safer, Inclusive and Sustainable
Schools Project held at the Mircești School, Iași county. The meeting was attended by the PMU team
made up of 6 members (consultants, designers, UMP coordinator) and the representatives of interested
parties from the community in the number of 20 people: the mayor of the town, the school director,
representatives of parents, students, teachers, counselors, educators, social workers, general secretary
of the city hall, local counselor, cultural center administrator and sports base administrator.
Fig.9 Photo from the initial public consultation held on March 8, 2023 in Mircești
Discussions were held based on the presentation of the project and the sketches/model made for the
future school. The participants asked various questions on issues related to access/exit routes, issues
related to digitization of the school, PSI points, getting approvals, facade colors, location of the library
and information center. All questions asked were answered on the spot, or recorded as future project
changes. The school principal asked questions about the school windows (how they will be opened,
what are the safety systems), questions about the first-floor guardrail, questions about the Information
Centre (separation from the library), whether a sports hall can be made, the local council representative
asks for clarification on the deadlines and timetable. The Mayor states that there is a lot of green space
outside and that there will be sports fields in this area.
"Vasile Alecsandri" Secondary School, Mircesti, Iași county
Recommendations that can easily Recommendations for interventions that Recommendations for
be implemented at school level can be addressed at project level interventions beyond the
without additional funding scope of the project that
can be submitted to the
MoE for consideration
No Including the dining room Gym
Interior and exterior wall colors
Raised handrail in the hallway
44
Pagina 45
The final conclusion was a positive one regarding the appearance of the school, the interior and exterior
details, the "open school" concept, the future facilities for the laboratories, exhibition areas, the
information centre and the library as spaces open to all, the existence of the dining room and the
colouring of the interior and exterior walls were the focus of the discussions.
45
Pagina 46
7. INVOLVEMENT OF INTERESTED PARTIES
The current ESMP is subject to a consultation process. The document is published on the Project website
from July 2023 for a period of 10 days. During this period, any interested stakeholders can provide
feedback to the document, identified risks and proposed mitigation and monitoring actions, through the
various channels provided by the Project.
After being published on the website, the document was disseminated locally by the school and local
authority, especially to teachers and parents of children who will be affected by the investment.
Additionally, an informative poster promoted the public consultation and was displayed at the Town
Hall, the school, and the Community Cultural Center.
The public consultation took place at the premises of the Mircești Primary School on August 2, 2023, at
12:00 PM, and was open to all interested parties.
The meeting was attended by the team of the Project Management Unit for the Modernization of the
School and University Network, consisting of 7 members (PMU coordinator, social consultant,
environmental consultant, area technical coordinator, designer, technical specialist, monitoring
specialist), as well as representatives of the stakeholders from the community, totaling 19 individuals:
municipal representatives (mayor, general secretary, procurement advisor, social assistant), school
representatives (principal, teachers, students), representatives of Iași County School Inspectorate.
Main topics:
- Consultation on the Environmental and Social Management Plan
- Presentation of the final version of the technical project
During the meeting, aspects related to the Environmental and Social Management Plan were discussed,
including the enumeration of environmental and social risks, their impact, and measures for their
mitigation.
The final version of the technical project was presented. Plans and renderings of the new building were
showcased.
The construction will have a height regime of Ground+1, a built area of 907 sqm, and a total area of 1750
sqm; with a maximum capacity of 156 students. The building will be equipped with fire detection,
signaling, and alarm systems, and an additional indoor fire hydrant network will be added as a
supplementary measure. The proposed functions will adhere to the initial design concept, with
additional inputs from the previous consultation phase, resulting in a school with 6 classrooms, 2
laboratories with dedicated storage rooms, a CDI space, a library, a dining hall designed for serving
meals in two shifts through catering, a medical room with isolation chamber, a psychological counseling
room with calming area, a designated area for teachers located on the first floor (office, secretary's
office, principal's office, a service room, and a waiting area), all of these spaces equipped with video
monitoring systems controlled from the technical rooms located on the ground floor.
Interior partitions will be made of BCA masonry, and the exterior joinery will be aluminum profile, with
glass ensuring thermal insulation. Interior joinery will also be aluminum, with solid and glass panels,
depending on the specific requirements of each space. Interior finishes will include PVC carpet floors in
vibrant, colorful shades (a play of colors), anti-slip ceramic tiles in wet areas (bathrooms), walls and
ceilings will be plastered, skimmed, and painted with highly washable paint, locally a suspended
plasterboard ceiling with sound-absorbing panels will be installed. The building will feature a
photovoltaic panel system connected to the distribution network, lighting will be achieved through LED
fixtures, and for intermittently used spaces, sensor-controlled fixtures with timers will be installed for
energy efficiency. Heating and cooling energy will be produced using renewable resources (solar panels,
46
Pagina 47
heat pumps), and sanitary installations will be equipped with sensors. Access for persons with
disabilities will be facilitated from the exterior through two ramps and from the interior via an elevator.
Fig. 10 Photo from the public consultation held on August 2, 2023 in Mircești
Conclusions: The attendees showed interest in the project-related information outlined in this
document, and it is planned to distribute it within the community.
The mayor of the community is highly enthusiastic about the technical project and emphasizes its focus
on educational and cultural activities. He gives priority to the safety and education of the children in the
community, and therefore, he will do everything within his competence to ensure the successful
completion of this project. The participants were also pleased, interested, and receptive. The next step
will be a community event (proposed by the social specialist) involving parents and children from the
locality to ensure that they are well-informed and have a direct platform to express their opinions and
suggestions regarding the project.
47
Pagina 48
8. GRIEVANCES MECHANISM
Within the project, a notification management and resolution system were developed, with the aim of
allowing the implementation team to receive information from the people affected by the project and
to be able to respond to their requests, thus managing, in an efficient way, the impact the project during
its implementation. On the project's website, there is a procedure on the complaint resolution
mechanism, which details the process at the PMU level.
Grievances related to the project can be submitted via several channels, as follows:
PMU level: The main four channels for receiving grievances are by website form, phone, e-mail and
mail at the level of the PMU. This ensures that the PMU has an immediate control over all project related
grievances and can address the raised issues immediately. The phone number of the secretariat will be
available on working hours.
Website form: www.umpmrsu.ro
Email: [email protected]
GBV Email*: [email protected]
Phone Number: +(4)(021) 310 22 07
Address: UMPMRSU, Spiru Haret, nr. 12, Sector 1, București
*In the case of complaints related to gender-based violence, additional attention will be paid to the
confidentiality and sensitivity of this type of petition. In order to ensure a fair and objective resolution
of the issues complained of by the complainant, the Project has established the use of a dedicated email
address, as well as a clear procedure for referring victims to specialized services provided by public and
private entities.
School Level: Stakeholders, affected persons, including students or parents, can submit their
grievances/suggestions at the school level through the grievance box that will be made available on
both the location of the construction site and the relocation site. These grievance boxes will be installed
at the time of relocation and beginning of works, and will be accompanied by a board describing the
Project and the current GRM and presenting all the channels that are available for the public to submit
their grievances.
In person: To ensure that the GRM is accessible to persons, that have no digital equipment or that have
low literacy levels, the Project provides the option to report complaint/feedback to the regional
coordinator or the PMU’s social specialist based on special dedicated feedback/grievance sessions
organized at local level. This option will be explored during public consultations and will be enacted
only when the scale of the impacts and the socio-economic conditions require for such an approach.
Such sessions will be announced in a timely manner and will be organized in an accessible location for
the affected persons.
The citizens will also have the option to address directly to PMUMSUN headquarters by planning a visit
with the social specialist or project manager in person.
Grievance mailboxes will be installed next to the school investment board before the commencement
of works at the level of each school site. The mailbox will be verified weekly by the area coordinator and
any grievances submitted by this channel will be sent immediately to the PMUMSUN by internal post.
World Bank GRS
The GRS ensures that complaints received are promptly reviewed in order to address project-related
concerns. The project affected communities and individuals may submit their complaint to the WB’s
independent Inspection Panel which determines whether harm occurred, or could occur, as a result of
WB non-compliance with its policies and procedures. Complaints may be submitted at any time after
48
Pagina 49
concerns have been brought directly to the World Bank's attention, and Bank Management has been
given an opportunity to respond.
For information on how to submit complaints to the World Bank’s corporate Grievance Redress Service
(GRS), please visit http://www.worldbank.org/GRS. For information on how to submit complaints to
the World Bank Inspection Panel, please visit www.inspectionpanel.org.
.
49
Pagina 50
ANNEX 1 - REQUIREMENTS AND MEASURES WHEN HANDLING ASBESTOS
Asbestos is a group of naturally occurring fibrous silicate minerals. It was once used widely in the
production of many industrial and household products because of its useful properties, including fire
retardation, electrical and thermal insulation, chemical and thermal stability, and high tensile strength.
Today, however, asbestos is recognized as a cause of various diseases and cancers and is considered a
health hazard if inhaled. Because the health risks associated with exposure to asbestos area now widely
recognized, global health and worker organizations, research institutes, and some governments have
enacted bans on the commercial use of asbestos.
In the European Union the use of asbestos is banned since January 1, 2005, and in Romania through a
Governmental Decision no. 734/2006 this was banned only for new materials. Products containing
asbestos and which have been installed or were in operation before the date 1 January 2005 can be used
until the end of their lifecycle.
Good practice is to minimize the health risks associated with ACM by avoiding their use in new
construction and renovation, and, if installed asbestos-containing materials are encountered, by using
internationally recognized standards and best practices to mitigate their impact. In all cases, the World
Bank expects borrowers and other clients to use alternative materials wherever feasible. ACM must be
avoided in new construction.
In reconstruction, demolition, and removal of damaged infrastructure, asbestos hazards must be
identified and a risk management plan adopted that includes disposal techniques and end-of-life sites.
Asbestos-containing (AC) products include flat panels, corrugated panels used for roofing, water
storage tanks, water, and sewer pipes etc. Thermal insulation containing asbestos and sprayed asbestos
for insulation and acoustic damping were widely used through the 1970s and should be looked for in
any project involving boilers and insulated pipes.
As asbestos is often used in construction (mainly for roofing) in many countries including Romania, it
can present a risk for the health of workers and population, who live near buildings that need capital
repair with replacement of roofing or demolition.
PMU specialists must inform beneficiaries on potential risk for their health and instruct not using
asbestos as construction material during construction/rehabilitation works.
Any asbestos product or material that is ready for disposal is defined as asbestos waste. Asbestos waste
also includes contaminated building materials, tools that cannot be decontaminated, personal
protective equipment and damp rags used for cleaning. Always this type of waste must be treated as
‘Hazardous Waste’.
In this regards, ACM and asbestos waste must be properly removed, stored in a separate closed area
and disposed (with the consent of local administration and environmental inspectors) on a landfill on
the special area for disposal of that type of waste.
PMU must require the contractors that the removal, repair, and disposal of ACM shall be carried out in
a way that minimizes worker and community asbestos exposure. During reconstruction works, workers
must avoid destroying asbestos sheets and properly dispose them at construction sites until final
disposal happens. Workers must wear protective over garment, gloves and respirators during work
with asbestos sheets. Proper disposal of ACM is important not only to protect the community and
environment but also to prevent scavenging and reuse of removed material. ACM must be transported
in leak tight containers to a secure landfill operated in a manner that precludes air and water
contamination that could result from ruptured containers. The removal and disposal of ACM and
asbestos waste as well as all other ESMP measures have to be included in both the technical
specifications and bill of quantities (BoQs). Contractor shall develop site-specific ESMP where
requirements to ACM and asbestos waste will be contained.
50
Pagina 51
ANNEX 2 - PROCEDURE FOR MANAGEMENT OF PHYSICAL CULTURAL RESOURCES –
PROTECTION AND CHANCE FIND PROCEDURES
Project construction activities have the potential to result in negative impacts on both tangible and
nontangible cultural heritage, which can be held as highly valuable within local communities and often
also at a regional level. Some cultural heritage sites may also be tourist attractions that help support
local economies. The Project and ESMF seeks to proactively manage, avoid or limit any negative impacts
on cultural heritage and to this effect has included specific obligations regarding cultural heritage in the
tender documents issued to potential Contractors.
Activities, such as trenching that may result in psychical impacts on culturally significant structures or
artifacts, including currently unknown artifacts, or construction could cause disruption to cultural
practices due to obstruction of access to cultural sites.
If any person discovers a physical cultural resource, such as (but not limited to) archeological sites,
historical sites, remains and objects, or a cemetery and/or individual graves during excavation or
construction, the Contractor shall:
1. Stop the construction activities in the area of the chance find;
2. Delineate the discovered site or area;
3. Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities
or sensitive remains, a night guard shall be arranged until the responsible authorities take over;
4. Notify the Supervising Engineer who in turn will notify the responsible authorities immediately
(within 24 hours or less);
5. Responsible authorities are in charge of protecting and preserving the site before deciding on
subsequent appropriate procedures. This would require a preliminary evaluation of the findings to be
performed by archeologists. The significance and importance of the findings should be assessed
according to the various criteria relevant to cultural heritage; those include the aesthetic, historic,
scientific or research, social and economic values;
6. Decisions on how to handle the finding shall be taken by the responsible authorities. This could
include changes in the layout (such as when finding an irremovable remain of cultural or archeological
importance) conservation, preservation, restoration and salvage;
7. Implementation for the authority decision concerning the management of the finding shall be
communicated in writing by relevant local authorities; and
8. Construction works could resume only after permission is granted from the responsible local
authorities concerning safeguard of the physical cultural resource.
The provisions presented above should always be included in ESMPs as a precautionary measure
regardless of a site having known or unknown cultural heritage or physical cultural resource
51
Pagina 52
ANNEX 3 - FORM FOR SUBMITTING SUGGESTIONS / COMMENTS
MINISTRY OF EDUCATION,
Project Management Unit for the Modernization of the School and University Network
„Safer, Inclusive and Sustainable Schools Project”
Bucharest, Sector 1, 12 Spiru Haret Street, 2nd floor
Feedback / petition* Form
School _________________________________ Locality__________________________________
* The completion of personal data is only necessary if you want this information to be treated as a
Petition and to receive a response, according to the regulations in force. In this case, it is necessary to
submit your request, complaint, referral or proposal through one of the following channels:
- In writing to the Project Management Unit (U.M.P.M.R.S.U.) of the Ministry of Education, str. Spiru
Haret nr. 12, Sector 1 Bucharest
- By the contact form on the U.M.P.M.R.S.U. website, - umpmrsu.ro
- by email at [email protected]
The information provided anonymously through this form will be taken into account and will be verified
and used for the purpose of improving the Project implementation activities and improving its impact.
Name and Surname
(Name of the entity)
Home County_______________________ Locality_________________________
(Headquarters) Street __________________________ No.______ Bl. ________ Ap._____
Contact information: □ By mail: (indicate your mailing address only if it is different from your home
(Please tick the ways in address)
which you would like to County________________________ Locality______________________
be contacted) Str. __________________________ No. ______ Bl. __________ Ap._____
□ Phone _______________________________________
□ Email _________________________________________
□ Other (indicate) __________________________________
Content of the petition/information in brief: (Please provide as full a description as possible of the
issues you wish to raise, what happened, when, who was involved, context, etc.)
Date: Signature:
____________________________ ________________________________
52